BBS Architects Engineers

Des Moines Airport

Des Moines Airport Terminal
Des Moines Airport Terminal

Owner: Des Moines Airport Authority

Project Data: 33,000 SF

Construction Cost:

Lower Level and 2nd Floor - $500,000

Terminal Lobby - $2,000,000

Construction Completed: 2011

Passenger wayfinding and operational efficiencies were improved with common use passenger processing system (CUPPS). New terrazzo flooring and undulating ceiling accents feature splashes of color and patterns enhancing wayfinding from the ticketing lobby to the concourses and from the concourses to baggage claim and ground transportation areas. The new architectural finishes in the concourses coordinate and compliment the aesthetics previously established in security checkpoint areas.

All construction activities were organized in phases and scheduled at night to facilitate continuous operations throughout the project’s duration.

Ames Lab Metals Development Air Handling Unit Replacement
Camp Dodge Pool Campus Improvements
Iowa City Federal Building - VHA Renovations
Des Moines Public Market
Richard Bolling Federal Building Study and Arc Flash Assesment
Covered Walkway
Iowa Events Center
Camp Dodge Urban Assault Course
Federal Building Study and Arc Flash Assessment
DSM Airport Energy Effiency Improvements
Hospital Emergency Room Renovation & Expansion
Executive Suites Renovation
Ames Laboratory Metal Development and Wilhelm Hall Electrical Study
Camp Dodge Chapel Addition and Renovation
Dodge House Renovations
© 2024 BBS Architects | engineers, All rights reserved.