Des Moines Airport

Des Moines Airport Terminal
Des Moines Airport Terminal

Owner: Des Moines Airport Authority

Project Data: 33,000 SF

Construction Cost:

Lower Level and 2nd Floor - $500,000

Terminal Lobby - $2,000,000

Construction Completed: 2011

Passenger wayfinding and operational efficiencies were improved with common use passenger processing system (CUPPS). New terrazzo flooring and undulating ceiling accents feature splashes of color and patterns enhancing wayfinding from the ticketing lobby to the concourses and from the concourses to baggage claim and ground transportation areas. The new architectural finishes in the concourses coordinate and compliment the aesthetics previously established in security checkpoint areas.

All construction activities were organized in phases and scheduled at night to facilitate continuous operations throughout the project’s duration.

Hub Tower Conference Center
New Facility
MacKay Hall Auditorium Renovation
Wyoming Farm Bureau Center
ETRC Howe Hall
Corporate Headquarters
New Office
VRAC C6 and Office Suite
Arizona Farm Bureau Center
Biological Sciences Facility
Covered Walkway
Geoffroy Residence Hall
Office Renovation
Coover Hall Infrastructure Study
Levitt Center for University Advancement
219 Eighth Street
Corporate Highrise
Camp Dodge Pool Campus Improvements
Corporate Headquarters Renovation
Beardshear Hall Remodeling
Home Office Building with Expansion
Minnesota Farm Bureau Center
College of Human Sciences
LeBaron Hall Replacement Study
Catholic Pastoral Center Rehabilitation
Kemin Food Sciences Lab Renovation
ETRC Hoover Hall
Hub Tower Office Tenant Improvement
Hospital Emergency Room Renovation & Expansion
Executive Suites Renovation
Reid “E” Research Facility
Dodge House Renovations
Utah Farm Bureau Center
Sabin Hall Renovation – LEED Gold
Extension 4-H Youth Building
Parking Garage
Iowa Events Center
© 2019 BBS Architects | engineers, All rights reserved.