BBS Architects Engineers

Iowa State University

Owner: Iowa State University
Architectural and Engineering Design Services: BBS Architects | Engineers
Construction Completed: October 2018
 

Client Need 
The existing steam line serving Lied Rec Center was in need of replacement.  Replacement of this line would be difficult and costly due to the conflicts with several other utilities and Lied Rec was now the only building served by this line.  ISU Utilities choose to abandon the existing steam line serving Lied Rec and provide a new gas-fired heating water plant within the building to meet building heating and domestic water needs.  
Approach 
The existing steam pressure reducing station, steam-to-water heat exchangers and heating water pumps for the building are located in a second floor mechanical room that also contains several air handlers.  Locating the new boiler plant in place of the existing steam infrastructure made sense but two key issues needed to be addressed: maintaining domestic hot-water and building reheat during construction and separating the boilers from the mechanical room that functioned as a return air plenum.  This involved creating a phased construction plan during design, which allowed for 100% availability of domestic hot water, and providing a new Boiler Rm within the existing mechanical room.
Solution 
Four new gas-fired heating water boilers comprise the new heating water plant.  One of the boilers is a condensing style and the other three are non-condensing.  With existing heating devices sized for a higher heating water temperature, it did not make sense to provide all condensing boilers for the building, when the system would only operate in a condensing mode during the summer.  Domestic water heating is provided by plate-and-frame water-to-water heat exchangers that are fed by the new boiler plant.  New correctly sized heating water distribution pumps with VFDs are provided.  A new room was constructed around the new boilers.  New electrical service was extended to the new equipment.  ISU Utilities provided new gas service to the building for the new boilers. 
 

Hub Tower Conference Center
Headquarters Building
Beardshear Hall Remodeling
Global Neighbors
Utah Farm Bureau Center
Food Sciences Building - Room 2379 Renovation
Coover Hall Infrastructure Study
Catholic Pastoral Center Rehabilitation
Reid “E” Research Facility
LeBaron Hall Replacement Study
DSM Airport Energy Effiency Improvements
EMC 219 Eighth Street
Dodge House Renovations
Terminal
VRAC C6 and Office Suite
Minnesota Farm Bureau Center
Ames Lab Metals Development Air Handling Unit Replacement
Geoffroy Residence Hall
Common Ground - Coffee Shop
Union Drive Community Center Renovations
Biological Sciences Facility
Corporate Highrise
IADA Office Renovation
ETRC Hoover Hall
BBS at 219 8th Street
Iowa City Federal Building - VHA Renovations
Iowa Events Center
Parking Garage
Sabin Hall Renovation – LEED Gold
MacKay Hall Auditorium Renovation
Extension 4-H Youth Building
Lance and Ellie's Sandwich Shop
Lincoln High School Improvements
Administration Building Renovation and Addition
Beardshear Hall Office Renovation
Theodore Roosevelt High School Natatorium Improvements
Corporate Headquarters Renovations
Levitt Center for University Advancement
Camp Dodge Pool Campus Improvements
Memorial Union Food Court
Executive Suites Renovation
Science Center - New Facility
Office Renovation
Covered Walkway
ETRC Howe Hall
New Office
Foth Companies Des Moines Office
ABC - Office Build-Out
Kemin Food Sciences Lab Renovation
Moulton Performing & Visual Arts Signature School
College of Human Sciences
Camp Dodge Chapel Addition and Renovation
Hospital Emergency Room Renovation & Expansion
© 2026 BBS Architects | engineers, All rights reserved.